Why Shutdown Windows Matter
Many plants, warehouses and distribution centres run around the clock. For these facilities, a planned shutdown is often the only time of year when the floor can be repaired, coated and marked without stopping production. The window is short and fixed, and the floor must be ready when the facility starts up again. We plan every shutdown project around that date. Request a free estimate as soon as your shutdown dates are set.
Choosing the System for Your Window
We offer several commercial and industrial flooring systems with different cure times. We select the system based on how long the space is available and how the floor will be used. When the shutdown window is tight, we can use a fast-cure system with a shorter recoat window, allowing our crew to apply successive coats sooner.
We typically complete surface preparation and coating application one day before handoff, leaving the final day for cleanup and a walkthrough with your team.
How Much Floor Fits in a 3-, 5- or 10-Day Shutdown
On one project, we completed diamond grinding and coating application across 24,000 sq ft in four days, averaging approximately 6,000 sq ft per day. The building was new, and our crew had uninterrupted access to the entire open floor.
Every facility is different, so for each shutdown we estimate how much flooring we can prepare, coat and return to service within the available window. The main factors are:
- Existing coatings that must be removed
- Concrete repairs, joints and pitting
- Phased access around equipment, racking and areas that must stay open
- The number of coats in the specified system
- The cure time required before traffic returns

Eaton Electrical Facility, Milton
Approximately 9,000 sq ft of epoxy flooring installed during the facility's Christmas shutdown, including Safety Blue pedestrian walkways and grey forklift traffic areas, with 4-inch safety markings and red stop bars throughout.
Returning to Service
Before work begins, we confirm in writing when each area can reopen to foot traffic, forklifts and full production. With our fast-cure system, once forklift traffic is permitted, we ask operators to avoid aggressive driving, sharp turns and hard braking for the first 72 hours after the final coat. The system reaches full cure in five days.
Other Shutdown and After-Hours Projects
- Green World Food Express, Mississauga: approximately 5,000 sq ft of freezer and cold storage floor with a 3-coat polyurethane waterproofing system, installed over one weekend from Friday afternoon to Sunday afternoon. Read the case study.
- Shawarma Royale restaurants: flooring installed at new locations during regular hours or overnight, depending on the construction schedule and site access.
- Event venue kitchen: a moisture vapour barrier epoxy system on 1,100 sq ft, installed during a two-day Easter shutdown.
Book as soon as your dates are set. Early notice gives us time to assess the concrete, confirm the flooring system and coordinate access with your operations team. If parts of the facility need to remain operational, we can schedule the work in phases, overnight or over a weekend.
Pricing Factors
Shutdown projects are quoted after a free site assessment. Pricing depends on the area, the condition of the slab, coating removal and repairs, the system and number of coats, safety markings, and how much of the work must be completed overnight, on weekends or within a fixed shutdown window. See our industrial epoxy flooring page and our guides to overnight installations and phased warehouse floor upgrades.