Case Study: Eaton Electrical Facility Christmas Shutdown

How Supreme Epoxy installed 9,000 sq ft of 3-coat epoxy with safety lines, stop bars and stencils at an Eaton electrical facility in Milton during a six-day Christmas shutdown.

ClientEaton electrical facility, Milton, Ontario
AreaApproximately 9,000 sq ft
System3-coat epoxy system with Safety Blue walkways, 4-inch Safety Yellow lines, red stop bars and stencils
Timeline6 days during the December 2025 Christmas shutdown

Eaton required a new coated and marked floor at its electrical facility in Milton, Ontario. The work could only take place while the facility was closed for the Christmas holidays, from 3 p.m. on December 23, 2025 to December 30. Supreme Epoxy completed the full 9,000 sq ft, including all safety markings, in six days. Request a free estimate to discuss your project.

The Challenge

An active electrical facility cannot stop operations for a floor project during the working year. Surface preparation, three coats of epoxy and the full set of safety markings all had to be completed and cured within the holiday shutdown, so the floor was ready when staff returned.

The layout also had to be clear and consistent. Aisles needed defined edges, and every point where routes meet needed a visible stop marking.

The System

We installed a 3-coat epoxy system with a layout that separates people from forklifts. Pedestrian walkways are Safety Blue, bordered by 4-inch Safety Yellow lines and finished in Carboline epoxy. Forklift areas are grey, and red stop bars with STOP stencils act as stop signs for forklifts where routes meet. The high-gloss finish is seamless and easy to clean.

Eaton electrical facility floor with Safety Blue pedestrian walkways, yellow safety lines, grey forklift areas and red STOP stencils by Supreme Epoxy
Eaton Electrical Facility | 3-Coat Epoxy with Safety Markings

Working Within the Christmas Shutdown

Work began at 3 p.m. on December 23, the afternoon the shutdown started. A crew of seven completed the surface preparation and all three epoxy coats. A crew of four then installed the safety lines, stop bars and stencils. The project was completed in six days, ahead of the end of the shutdown window.

Walkway intersection with yellow lines, red stop bars and STOP stencils on a grey and blue epoxy floor
Aisle Intersection | Stop Bars and Stencils
Grey epoxy aisle with a red stop bar and STOP stencil between blue borders
Stop Point | Red Stop Bar and Stencil

The Result

  • Approximately 9,000 sq ft coated and marked
  • A 3-coat epoxy system with Safety Blue pedestrian walkways and grey forklift areas
  • 4-inch Safety Yellow lines, with red stop bars and STOP stencils for forklifts
  • A seamless, high-gloss surface that is easy to clean
  • Completed in six days within the Christmas shutdown

Client Feedback

The Eaton team was very pleased with the transformation. They appreciated the professional finish and how clearly the new floor markings distinguish forklift travel lanes from pedestrian zones.

Long high-gloss grey epoxy aisle with yellow edge lines and a blue border in an electrical facility
Completed Aisle | High-Gloss Epoxy Finish

Warehouse and Industrial Floors

Plants and warehouses need floors and markings planned around production. We review the layout, test the concrete and schedule the installation around shutdowns, weekends or holidays. See our warehouse epoxy flooring and warehouse safety line marking pages, or book a free site assessment.

Project work